PERI solution
In order to provide safe working conditions around both the interior and exterior of the silo structure, as well as the means to form the structure walls, climbing units were created by combining PERI’s TRIO wall formwork with its Climbing System CB240, complete with a formwork carriage. The large 5.0 m wide platforms were easily lifted using a single crane lift.
The working platform of the Climbing System CB240 is created using the CB240 Climbing Brackets. The wall formwork is then mounted on the platform using the Carriage CB 240, strong backs and adjustable spindles. The carriage provides an easy way to move the TRIO wall formwork forwards or backwards. When fully retracted, there is 750 mm of safe working space in behind the formwork.
An additional feature of the Climbing System CB240 is the option to incorporate a finishing platform below the working platform. The finishing platform allowed crews to retrieve re-usable anchor components and to finish the concrete face. The exterior wall face of the silo required a high quality concrete finish, so an additional layer of plywood was mounted on the TRIO panels; the inside wall face used the standard TRIO FormPly.
Columns, which had to be poured in two lifts, were cast in place using the QUATTRO Column System. PERI UP scaffolding was erected around the columns to provide a safe working platform for site personnel and to support the formwork for the second pour. PERI UP stair towers provided access to the platform levels. The QUATTRO column forms were lifted in place for the pour above as a complete unit with one crane lift.