Elite Formwork Inc. decided to use the PERI UNIPORTAL table system. By using this system, tables ranging in size from 16 ft x 26 ft (4.80 m x 8.00 m) were effectively flown by using the self leveling C-Hook.
|
|
On this project, PERI supplied the SKYDECK slab formwork system, TRIO wall formwork and KG climbing brakkets.
|
|
PERI SKYDECK system uses a drophead technology which allows the shores to stay in place during the stripping procedure.
|
|
PERI‘s ACS (Automatic Climbing System) was chosen for this project because Findorff wanted to run the shear walls ahead of the horizontal slabs.
|
|
The Lakeshore East development area in Chicago is a 26 acre parcel of land located on the South bank of the Chicago River at Lake Michigan. This area will be a host to over 25 new structures in the next few years.
|