RCMP E Division’s New Headquarters, Surrey, British Columbia
Innovative PERI formwork systems help institutional project be completed ahead of time
On a 14-hectare site in Surrey B.C., the new $966 million RCMP head quarters building is under construction. The principal building on the site will be the Operations Administration Building which will be 7 storeys high, and contain a total floor area of 65,017 square meters. Syber concrete forming is using 80 SKYTABLEs to achieve construction of 4,650 square meters of 4.00 m high slabs per week.SKYTABLE allows concreting large area slabs with only one crane pick. The largest table on this site is 5.70 m wide and 22.40 m long. The tables were designed to weigh less than 6,000 kg to conform to the crane capacity.
|
| PERI Systems In Use |
SKYDECK Aluminum Slab Formwork System
MULTIPROP Slab prop
MULTIFLEX Girder Slab Formwork
SKYTABLE Tableforms
|
|
Steve Beaton, Construction Manager:
“With the PERI SKYTABLE we are able to pour 50,000 Sq. ft of slab a week. The guys on site like to work with the system, because it’s not heavy and is easy to use. The flying process is safe and fast. Using PERI on a proposed six months job we are going to save a lot of time and will finish two month earlier.“
|
|
Contractor
Syber Concrete Forming Ltd.
Field Service
PERI Vancouver
|
|
Field Service:
|
PERI Formwork Systems, Inc., Canada
|
|
|